Year of 2006:
Behling Road - Clear and Grub - (Completed)
Dereg Road - Blacktop - (Completed)
Selmer Road - Blacktop - (Completed)
Swanson Road - Recondition and Blacktop - (Completed)
Wadell Road - Shoulder and Ditch - (Some Ditching Completed)
Tannery Road - Repair at CTY CC intersection - (Completed)
Stone Road - Recondition and get ready for blacktop - (Completed)
Cottage Road - Survey for relocation
Kings Road - Shoulder clean up - (Completed)
If funds are available for 2006:
Sunset Point Road - South of HWY 86 - Recondition and Blacktop - (Completed)
Spirit View Road - Recondition and Blacktop - (Completed)
Year of 2007:
Koth Road - Clear and Grub - (Clearing Completed)
Kings Road - Blacktop from CTY D to around the corner from the Log Jam - (Completed)
Beach Road - Clearing - (Completed)
Deer Lake Road - Clear and Grub
Stone Road - Blacktop - (Completed)
Peaceful Valley Road - Brush and Grub - (Brushing Completed)
Wadell Road - Additional road work depending on finances