   Year of 2011:

   Alery Rd. – From CTH E to .2 Tenths of a Mile Past Blum Rd. – Pulverize, Add base, and Resurface – Completed

   Blum Rd. – Allery Rd. to Rock Falls Line – Pulverize and Gravel – Completed

   Stelling Rd. – Pulverize, Add Base, and Resurface – Completed

   Wadell Rd. – From CTH E to 3/4th of a Mile – Add Base and Surface – Completed

   Swamp Rd. – Re-Gravel – Completed

   Norton Rd. – Clean Shoulders and Grub – Completed

   Norlander Rd. – Clean Shoulders and Grub – Completed

   Road Lake Rd. – Clean Shoulders and Grub – Completed

   Curve Inn Rd. – Replaced Culverts – Completed

   Peaceful Valley Rd. – From Coda Ln. to End – Clear and Grub – In Progress

   Milky Rd. – Clean Shoulders and Grub – In Progress

   Kablitz Rd. – Clean Shoulders and Grub – In Progress

   Red Pine Rd. – Clean Shoulders and Grub – In Progress


   Year of 2010:

   Deer Lake Rd. & Deer Lake Rd. East – Recondition, Pulverize, Add Base, and Resurface – Completed

   High View Rd. – Pulverize, Add Base, and Resurface – Completed

   Alber Rd. – From CTH O to 1950’ – Resurface – Completed

   Alery Rd. – Widen, Ditch, and Remove Corduroy – Completed

   Stelling Rd. – From CTH E to .2 Tenths of a Mile – Clean Ditches – Completed

   Norten Rd. – Clean Shoulders – Completed

   Beaver Lake Rd. – Re-Gravel – Completed

   Kyes Rd.  – End of Kyes Rd. Blacktop to Town of Skanawan Line – Re-Gravel – Completed 

   Alery Rd. – .2 Tenths of a Mile Past Blum Rd. to End – Re-Gravel – Completed

   Red Pine Rd. – Re-Gravel – Completed

   Gravel Crushing – Re-Supply Storage Pile – Completed

 This 2 year plan is subject to change depending on finances and unforeseen problems.


   Possibly 3rd Year Options:

 

   Norton Rd. – Pulverize, Add Base, and Resurface

   Road Lake Rd. – Pulverize, Add Base, and Resurface

   Curve Inn Rd. – Pulverize, Add Base, and Resurface

   Peaceful Valley Rd. – Coda Ln. to End – Pulverize, Add Base, and Resurface

   Moodig Rd. – From Muskellunge Lake Rd. South over Swamp – Pulverize, Add Base, and Resurface

   Kablitz Rd. – Pulverize, Add Base, and Resurface

   Greenwood Rd. – Pulverize, Add Base, and Resurface

   Tamarack Ln. – Replace Culverts