Town of Bradley's
Proposed Road Projects for 2010-2011
Year of 2010:
Deer Lake Rd. & Deer Lake Rd. East – Recondition, Pulverize, Add Base, and Resurface
High View Rd. – Pulverize, Add Base, and Resurface
Alber Rd. – From CTH O to 1950’ – Resurface
Alery Rd. – Widen, Ditch, and Remove Corduroy
Stelling Rd. – From CTH E to .2 Tenths of a Mile – Clean Ditches
Norten Rd. – Clean Shoulders
Beaver Lake Rd. – Re-Gravel
Kyes Rd. – End of Kyes Rd. Blacktop to Town of Skanawan Line – Re-Gravel
Year of 2011:
Alery Rd. – From CTH E to .2 Tenths of a Mile Past Blum Rd. – Pulverize, Add base, and Resurface
Alery Rd. – .2 Tenths of a Mile Past Blum Rd. to End – Re-Gravel
Blum Rd. – Allery Rd. to Rock Falls Line – Pulverize and Gravel
Stelling Rd. – Pulverize, Add Base, and Resurface
Wadell Rd. – From CTH E to 3/4th of a Mile – Add Base and Surface
Peaceful Valley Rd. – From Coda Ln. to End – Clear and Grub
Re-Gravel – Either Swamp Rd. or Red Pine Rd.
This 2 year plan is subject to change depending on finances and unforeseen problems.
Possibly 3rd Year Options:
Gravel Crushing – Re-Supply Storage Pile
Norton Rd. – Pulverize, Add Base, and Resurface
Road Lake Rd. – Pulverize, Add Base, and Resurface
Curve Inn Rd. – Pulverize, Add Base, and Resurface
Peaceful Valley Rd. – Coda Ln. to End – Pulverize, Add Base, and Resurface
Milky Rd. – Clean Shoulders and Grub
Moodig Rd. – From Muskellunge Lake Rd. South over Swamp – Pulverize, Add Base, and Resurface
Kablitz Rd. – Pulverize, Add Base, and Resurface
Greenwood Rd. – Pulverize, Add Base, and Resurface
Tamarack Ln. – Replace Culverts